Queuing Rule of Thumb based on M/M/s Queuing Theory with Applications in Construction Management

Authors

  • Kardi Teknomo Department of Information System & Computer Science, Ateneo de Manila University, PHILIPPINES.

:

https://doi.org/10.9744/ced.14.3.139-146

Keywords:

Rule of thumb, constraint equation, concreting, earth moving.

Abstract

The current trend of queuing theory development is toward more precision which requires higher mathematical manipulation. In this paper, we attempted to reverve the current trend toward simplification of queuing formulas such that it can be used in more practical purposes, especially in construction industry. Through numerical examples of two case studies on concreting and earth moving, how to model the construction activities as queuing systems is illustrated systematically. Through the numerical examples, it is shown that when the customer cost is much lower than the server cost, queuing system can be simplified only to incorporate the constraint equation. The queueing constraint equation is suggested to be used as queuing rule of thumb. The proposed rule of thumb is rather conservative in term of queuing performance compared to the standard stochastic queuing formula because it is assumed that all the customers arrive at once in the beginning of the service.

References

Hendrickson, C. and Tung, A., Project Manage-ment for Construction - Fundamental Concepts for Owners, Engineers, Architects and Builders, Prentice Hall, 1998. http://pmbook.ce.cmu.edu/ 04_labor_material,_and_equipment_utilization.html.

Oberguggenberger, M., Queueing Models with Fuzzy Data in Construction Management in: W. Fellin et al (Editors) Analyzing Uncertainty in Civil Engineering, Springer, 2004. pp. 197-208.

http://www.globalspec.com/reference/34589/ 203279/ queueing-models-with-fuzzy-data-in-construction-management

Cheng, M.Y., Tsai, H.C., and Lai, Y.Y., Construc-tion Management Process Reengineering Perfor-mance Measurements, Automation in Construc-tion 18, 2009, pp.183-193. http://www.ct.ntust. edu.tw/ct/filesConstruction%20management%20process%20reengineering%20performance%20measurements. pdf. See also: http://140.118.5.71/bpr%20 files/Bpr_ Evaluation.pdf.

Tian, N. and Zhang, Z.G., Vacation Queueing Theory Model – Theory and Application, Springer, 2006.

Yue, W. et al., Advances in Queueing Theory and Network Applications, Springer, 2009. [CrossRef]

Hall, R.W., Queueing Methods for Services and Manufacturing, Prentice Hall, 1991.

Carmichaela, D.G., Shovel–truck Queues: a Reconciliation of Theory and Practice, Construction Management and Economics, 4(2), 1986, pp.161-177. http://www.tandfonline.com/doi/abs/10.1080/01446 198600000013.

Downloads

How to Cite

Teknomo, K. (2012). Queuing Rule of Thumb based on M/M/s Queuing Theory with Applications in Construction Management. Civil Engineering Dimension, 14(3), 139-146. https://doi.org/10.9744/ced.14.3.139-146